Degraded T2 requiring full renovation

Project Objective
Renovation of a two-bedroom apartment (63 m²) in poor condition, including a 50 m² yard.
The entire process, from acquisition to sale, was completed in 10 months.
The investment partner generated 28.950€ in gross profit, equivalent to a 27% return.
Project Details
57.000 EUR
36.700 EUR
10 months
Through renovation
Asset repositioning and optimized sale to maximize returns
Process
The project involved a full refurbishment with structural repairs, replacement of plumbing, sewage and electrical systems, and layout modernization. Renovation costs totaled 36.700 EUR, with 9.700 EUR in sales intermediation costs, bringing the total investment to €107.100 EUR.
Before
After